IT Data Suite Removal

Axis were contracted to remove a redundant IT data suite from a financial institution in Canary Wharf to create 60 new desk positions. We were awarded the role of Principal Contractor and to ease disruption and ensure business could continue as normal we operated on a 24-hour basis to condense the project to a 12 week programme, conducting any intrusive, noisy or disruptive works outside of normal working hours.

The scope of works included installing a new ceiling and a new raised floor to match the existing system present in the rest of the building following the removal of the IT data suite. Decorative works such as painting and new flooring completed the project and the result was a bright, open space for the new desk positions.